Home » Patient & Visitors » Construction Update » Construction Timeline
Construction Timeline
 

The following are key activities taking place over the coming weeks in the Campus Expansion Project. If you have questions about an aspect of the project call Tom Urtz (540) 536-5150.

Winchester Medical Center

Campus Expansion Project

Monthly Work Summary

June 2010

 

Wk of 06/01/10

top out of Lab steel

Wk of 06/01/10

top out of H&V steel

Wk of 06/10/10

North Tower crane set-up

Wk of 06/14/10

begin North Tower steel erection

Wk of 06/21/10

open new east Loading Dock

July 2010

 

continue exterior and interior framing at H&V

continue exterior framing at Lab

Wk of 07/05/10

begin west Loading Dock demo

Wk of 07/05/10

begin masonry at Lab

Wk of 07/05/10

begin masonry at H&V

Wk of 07/12/10

begin masonry at Tank Farm

Wk of 07/12/10

steam shutdown

Wk of 07/20/10

begin new west Loading Dock

August 2010

 

Wk of 08/07/10

electrical shutdown

Wk of 08/11/10

begin erecting steel over Loading Dock

Wk of 08/23/10

open west Loading Dock

Wk of 08/23/10

open detour and Elevator 2

Wk of 08/30/10

open new Radiologist's Lounge

Wk of 08/30/10

H&V weather tight


 

 

 

 