Wk of 06/01/10
|
top out of Lab steel
|
|
Wk of 06/01/10
|
top out of H&V steel
|
|
Wk of 06/10/10
|
North Tower crane set-up
|
|
Wk of 06/14/10
|
begin North Tower steel erection
|
|
Wk of 06/21/10
|
open new east Loading Dock
|
|
|
|
July 2010
|
|
|
continue exterior and interior framing at H&V
|
|
continue exterior framing at Lab
|
|
Wk of 07/05/10
|
begin west Loading Dock demo
|
|
Wk of 07/05/10
|
begin masonry at Lab
|
|
Wk of 07/05/10
|
begin masonry at H&V
|
|
Wk of 07/12/10
|
begin masonry at Tank Farm
|
|
Wk of 07/12/10
|
steam shutdown
|
|
Wk of 07/20/10
|
begin new west Loading Dock
|
|
|
|
August 2010
|
|
|
Wk of 08/07/10
|
electrical shutdown
|
|
Wk of 08/11/10
|
begin erecting steel over Loading Dock
|
|
Wk of 08/23/10
|
open west Loading Dock
|
|
Wk of 08/23/10
|
open detour and Elevator 2
|
|
Wk of 08/30/10
|
open new Radiologist's Lounge
|
|
Wk of 08/30/10
|
H&V weather tight
|